Update on Thames Water work and irrigation system installation

The work by Thames Water on installing a water system for Plymouth Wharf at each end of the estate is due to be completed this week between Feb 28th– March 2nd. Obviously this will be dependent on the weather!

The irrigation system is then due to be installed next week starting March 5th. It is expected to take approx. 5 days.

Paviors will need to be lifted temporarily to make links from the top river bed to the middle bed and from the middle bed, at each end and on both sides, to the flower beds. This will not affect anyone’s car parking space but it may be necessary at times to drive the wrong way round the Wharf.

If you cannot reach your parking space at any time please park at either end of the Wharf, or in the Visitors spaces or in a space that you know is empty.

We apologise for any inconvenience and thank you for your cooperation.