Completion of redecoration works – Monday 12th July

Our contractors, SJS have now completed nearly all of the redecoration work. There are a few details to cover but Monday the 12th of July should be the last day. If anyone has an issue please email roberto.saas@plymouthwharf.com by Monday morning at the latest.

Before reporting an issue, something that was missed for instance, please make sure the area is free of obstacles and accessible to the contractors so they can finish the work. After Monday, the board will not recall the contractors at PWRA’s expense. 

The board would like to thank everyone for their patience and cooperation over the last few weeks during the redecoration works.

External painting and redecoration works – 17th May 2021

External painting and redecoration works will be undertaken across the whole development from 17th May 2021 for approximately 12-14 weeks. This work was originally planned for last year but had to be delayed due to the COVID-19 global pandemic. 

The works to be carried out under the agreement are in accordance with the section 20 process that has already been undertaken and previously shared with all shareholders/owners. A copy of the specification for the works has been previously shared and is available upon request to shareholders. In summary these works will include repainting of all block doors (communal and flat front doors), bannisters and handrails, gates, fences (front and rear) and any remaining wooden window frames.

The contract for the works has been awarded to SJS Maintenance.

Works will start on Monday 17th May on the riverside Blocks 2 & 3 (Properties #20-#43) for an expected 4 weeks. The following 4 weeks will be to complete central houses (#11-#19 and #44-#52). Finally the work will conclude with the two roadside Blocks 1 & 4 (Properties #1-10 and #53-#62) for further 4 weeks. In total, all works are expected to be finished between to 12 to 14 weeks.

Various contractor equipment and a storage container will be placed within the premises as well as a portable toilet (to be used for the contractors). Temporary restrictions on some of the parking spaces will therefore be in place.

Contractors from SJS Maintenance will be in and out for the whole duration of the works. They will be working Monday to Friday from 8am till 4:30pm.

Further important communications will be posted here website and via communal notice boards in each block during the works to advise on any steps residents need to undertake during the works.